Two Times of Hoisting in One Day “Combination of Chinese and Western Elements” - Offshore Work Resumption in Area 4 of Penglai 19-3 Oilfield Won the First Battle

Date:2020-03-04

On February 21, the main work boat “Blue Whale” of the Company successfully completed the hoisting of east and west modules of WHPK platform for Penglai 19-3 Oilfield Area 4 Adjustment / Penglai 19-9 Oilfield Phase II Development Project, which refers to the first offshore large-scale hoisting operation during epidemic prevention & control.

The successful hoisting of WHPK module raised the curtain of offshore connection and commissioning of Penglai Project, thus laying a solid foundation for subsequent mechanical completion as soon as possible.

On February 15, after “Blue Whale” stuck to the post for 22 days, they welcomed the construction personnel of WHPK module hoisting of Penglai 19-3 Oilfield Area 4 Project under the premise of good epidemic prevention & control. Beforehand, “Blue Whale” effectively docked and closely communicated with the PMT, developed a series of practical and feasible prevention & control measures, including the Boarding Process and Prevention & Control Requirements during Construction, “One Policy for One Ship”, and insisted on equal stress on epidemic prevention & control and production & operation. Before boarding, PMT orderly carried out epidemic prevention & control and adopted such measures as isolation of personnel for 14 days before construction, body temperature monitoring of personnel, and disinfection of personnel luggage and equipment. After boarding, PMT implemented such measures as dispersion of personnel, dispersion at dining time and body temperature monitoring every day. “Blue Whale” fought against the epidemic with all efforts in combination with the practical conditions, overcame all difficulties and rose to the challenges, to guarantee the successful completion of module hoisting of Penglai 19-3 Oilfield Area 4 Project.

During the offshore construction, “Blue Whale” did a good job in epidemic prevention & control and production arrangement to ensure safe and efficient construction, completed the offshore hoisting of two upper modules only in 10 hours, and excellently won the first battle after offshore work resumption.

Photo I: Module Hoisting

Photo II: Successful Hoisting of Module in Place