Services

Projects

COOEC-Fluor

Overseas Business

Brazil FPSO Project

Petrobras FPSO Project refers to the two FPSO ships (P67/P70) through cooperation with Petrobras, of which P67 has been successfully delivered and P70 is under integration at present. For these two ships, the dry weight of topside and hull is about 25,000 t and 53,000 t respectively, with designed oil production of 150,000 barrels/day, gas production of 6 million standard m3/day, and storage capacity of 1.6 million barrels (about 226,000 t).

This is the first project delivered by COOEC as an independent FPSO general contractor, which not only breaks the domestic record, but also creates the record of the first international FPSO project of COOEC, thus bringing precious experiences and reputation for COOEC in the world’s floating body market.